IT Courses: JFW/RJ (Word, Excel and Windows) – Completed in 1996. CCAA English Course: Completed in
2004. CIPA: Elected for the 2005/2006 and 2014/2015 administrations. NR-10 – Completed in 2019. NR-35 – Completed in
2018. NR-33 - Completed in 2018. NR-13 - Completed in 2018. NR - 20 - Completed in 2018. SAP– Done
in 2019. Fire Brigade - The course was held in 2006 and 2015. Yellow, Green and Blackbelt - Held in
2020 and 2021. Yellowbelt-Held in 2023
Responsible for the maintenance of the automation assets of the Abreu e Lima Refinery-PE;
Responsible for the elaboration of operating standards of automation assets;
Responsible for the execution of training for the qualification of the automation team;
Responsible for the technical supervision of QWS employees;
Responsible for the preparation of the loss profile of the refinery's automation assets
Abreu e Lima-PE.
Analysis of the Loss Profile of Ore Shipment at the Port of Madeira. Elaboration and
management of D-1 meetings and systemic treatment with the disciplines of the Port.
Execution of TAFs (Analysis Processing)
of Failures) by collecting the field information of asset failure events.
Perform analysis of the database of equipment failures at the Port of Madeira, to generate performance improvement projects.
Responsible for FF, HART, PROFIBUS, MODBUS and I&G network certifications; - Supervise field team; - Schneider foxboro IA Archestra DCS configuration, with interface of
communication Profibus, modbus, hart, Foundation Fieldbus;- Preparation of Technical Reports and investigation of causes of Trip in the Plant
Abreu e Lima Refinery in order to keep the plant in operation;- Act in the configuration of the Schneider Foxboro DCS database;- Elaboration/configuration of the AI foxview system screens;- Perform the Field Acceptance Tests of the Schneider Foxboro DCS System;- Monitor the mesh tests of the equipment that will be integrated into the
Schneider automation;- Validate the interconnection of panels to the Schneider DCS system;- Give technical support to EPC's and assemblers in the conditioning phases, pre-conditioning, pre-conditioning,
operation and assisted operation;- Validate the mechanical, electrical and interconnection installation in the field of equipment,
assembly of valves, positioners and calibration of them;- Monitor the Loop Test of the instruments;- Supervise the Physical Installation of the Schneider panels
Completion of the electrical and mechanical installations of the Inbetta Paulista PE plant
Completion of the industrial automation project of Queu e Lima RNEST
Completion of the electric power substation assembly project at CEASA-PE
Completion of the water treatment plant assembly project at CEASA-PE
Completion of industrial automation services at Klabin in Telêmaco Borba,
acting for Schneider
Participation in the Automation project of Vale's Salobo 3 unit
Presentation of the failure predictability project at ABRAMAN in 2023